Saturday, January 17, 2009

Second Week - January 12th

With renovation work there is almost always... Discoveries! The first week the doors and windows were removed, the wood framing was pulled off and the concrete floor removal was started. The floor was only supposed to take a couple of days, but we discovered that instead of 4 to 6 inches of concrete there was as much as 30 inches in some places! We also found the water line and one of the electrical cables with the concrete saw. As the paving people proceeded to lay out the project in detail (all those stakes and orange lines on the ground) we found that there were several questions that needed to be answered by our civil engineer. This resulted in a meeting, and some minor redrawing of the paving plan. Our General Contractor Rick Mouw needed to get involved but had the misfortune of a heart problem and is in the hospital! He and his new pacemaker are doing well, he says he'll be back at work Monday... Paving will be delayed but will not effect the completion date, shell construction is still very much on track to finish in time. Concrete floor removal work finished up and they moved on to the walls. This went more smoothly but sure looks like hard work. You can see that the roof is supported with extra beams and jacks until the wall is gone and a steel beam is installed.


Good news/Bad news. As the dissassembly work progressed we found that the roof leaks under the stained glass windows that we fixed last year had caused quite a bit of damage over the years. Also a small colony of carpenter ants had moved in. Patti Muranti's brother Tony sprayed and they moved out. All this will be fixed in the process of rebuilding - that would be the blessing part!
Please check out the pictures for this and previous weeks. Here is the link to the Week 2 pictures.

http://picasaweb.google.com/photos.sjecs/Narthex11209Week2?authkey=qI-PqRydr_Y#

Peace, Ric Filer

Week One - January 5th

Well it’s finally happened! As I’m sure you noticed we have actually started to “Make Room at the Inn”!
Monday January 5th at 7am the crew from Mouw Associates arrived with trucks and equipment and started setting up. By the end of the day the barricades were in place, scaffolding was up and St. Joseph and baby Jesus had been carefully moved from their place in the circle.
Tad Knutson’s crew transplanted several trees both large and small to make way for the new paving. During the week the front of the church was pulled apart and the old carted away in anticipation of the new. The interior was walled off to protect the rest of the church during construction. The Narthex itself will be finished in about three months.
The paving work will take only about four weeks and for a while change our driving habits since the center of the campus is completely blocked off.
On Sundays you can enter from either Seacrest or Swinton and the parking ministry folks will help you find the best spot. If you want to visit the church during the week, the Swinton entrance will be the best by far.

Take a look at the illustration below. If you enter from Seacrest and park in either the school lot or on the grass you will need to take a bit of a walk to avoid the work area. If you enter from Swinton the access is easier, the walk is shorter and there are still two handicap access areas. During the week the Seacrest gate will be open all day but closed after school is finished around 6pm.
Tami Pleasanton and her staff have done a masterful job and risen to the challenge of redirecting the school traffic mornings and afternoons and the students all day long. Thanks for being so cheerful about the whole thing!

There are colorized drawings of this phase of the work posted at the back of the church and in the parish hall that may help you visualize what the finished project will look like. Here's a link to some drawings.

http://picasaweb.google.com/photos.sjecs/109?authkey=o1jyBsVpshw#

Here's a link to the first week's photo album.

http://picasaweb.google.com/photos.sjecs/Narthex1509TheFirstWeek?authkey=lJnwwwnI8Zw#

I’ve been blessed to be part of the process of bringing our plans to reality. I’m also excited and thankful to finally get underway. Please let me know if you would like a closer look at what’s going on and I’ll be happy to provide the nickel tour…

Peace, Ric Filer

Jobsite Photo Albums

One of the duties we have taken on to save money is that of Jobsite Photos, I take hundreds every week. Here are links to all of them.

Ric

http://picasaweb.google.com/photos.sjecs/Narthex10908MeetWSchoolAboutTraffic?authkey=5MTMdP5q-yA#

http://picasaweb.google.com/photos.sjecs/Narthex121708HydrantMove?authkey=ODmKukeN1c0#

http://picasaweb.google.com/photos.sjecs/Narthex1209MovingDay?authkey=UNQhEQY1kAk#

http://picasaweb.google.com/photos.sjecs/Narthex1509TheFirstWeek?authkey=lJnwwwnI8Zw#

http://picasaweb.google.com/photos.sjecs/Narthex11209?authkey=0M2nr1VVumA#